Wind Park 2000 kW
Wind park in operation four wind turbines with a total installed capacity of 2 MW and expansion totaling 21 MW.
I. Land 152905 m2 :
1. 42631 m2
2 . 6931 m2
3 . 17388 m2
4 . 44637 m2
5 . 41318 m2
II. Wind turbines - 4 pcs. 500 kilowatts - Work with supporting infrastructure
III. Plan DDP / development / - 4. Visa to design a new 7 pcs. wind energy up to 3000 kilowatts each.
Important! First outside the TNG is the status of agricultural higher category. Priority will be leased . Additional revenue of about 10 000 leva per year.
Scope of Company construction and operation of facilities for the production of electricity and / or thermal energy from conventional and renewable sources , production and sale of electricity and / or heat conventional and renewable energy , the development and implementation of other investment projects home and abroad , as well as any other business and / or services that are not prohibited by law.
The Company's operations in North wind farm , located in the village Mogilishte of Kavarna Municipality .
Windmill " North" consists of four parts 500 kW wind turbines , each with a total installed capacity of two megawatts / MW 2 / on our land with an area of ​​11,587 hectares. Generators second-hand , recycled in Germany, with the following technical parameters :
generator 1
Model Vestas V39/500, power 500 kW , 39 m rotor diameter , 40 meter tower .
generator 2
Model STC 500/41/50 power of 500 kW , 41 m rotor diameter , 50 meter tower .
generator 3
Model STC 500/41/50 power of 500 kW , 41 m rotor diameter , 50 meter tower .
4 generator
Model Vestas V39/500, power 500 kW , 39 m rotor diameter , 40 meter tower .
Used to work as generators : transformer - 4 , three-phase power transformer - 3, switchgear, GRU , dashboard subsistence measuring cell , column , cable lines .
Mode of operation:
At the base of the tower of a wind turbine is a control panel with a computer that controls the behavior of the generator power system parameters , wind parameters and controls generatova. Fully automatic mode . At wind speeds lower than 4 m / sec . computer from the generator and locked rotor . In the wind speed exceeds 25 m / sec . actuated brake .
Wind connected to the distribution network of 20 kV substation " Kavarna " Aviation »Krupen. "
Accounting for electricity is on the side of 20 kV to 20 kV substation with existing electronic counters / buy-sell / bi-directional active and reactive power . Data collection from meters is carried out in the presence of representatives of the company and the electric company .
Wind farm expansion is carried out in their own land company. The resulting potential distribution network of 12 MW , which signed a preliminary agreement to join producer with power company E.ON. The turbines will be built will be connected to the substation "Varna" , the cable line connecting points of increasing turbine substation .
Our company has achieved sales in the project "North" is committed to providing the design wind farm to obtain all necessary permits or permissions that allow to provide the necessary assistance to the investor in the supply and installation of the wind and other help in all possible ways to insert the object into operation , the actual connection fleet expansion network and start generating electricity .